Professional Scrum Product Owner I PSPO I · Free Practice Question Easy
Question 11
When can new work be added to the Sprint Backlog?
(choose the best answer)
-
A
Only during Sprint Planning.
-
B
Whenever it is identified by the Developers.
-
C
Only when approved by the Product Owner.
-
D
Only when there is room in the Sprint Backlog.
Reveal correct answer
Correct answer: B
Explanation
According to the Scrum Guide, during a Sprint, new work or further decomposition of work is added to the Sprint Backlog as soon as possible after it is identified. The Sprint Backlog is a highly visible, real-time picture of the work that the Developers plan to accomplish during the Sprint in order to achieve the Sprint Goal.
Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.